PRC Approval Design Build
Design Build RFQ
- Determine budget specifically for RFQ effort, including stipends paid to unsuccessful finalists.
- Determine RFQ schedule.
- Draft project charter.
- Apply for Project Review Committee (PRC) approval.
- Complete and send Exposure Checklist form to Risk Management.
- Develop selection committee, packet and advertisement.
- Receive submittals, evaluate and score.
- Interviews and selection
- Finalize Design Build contract.
PRC Approval
Prepare Project Review Committee (PRC) documents and presentation, including DB Project Application and submit.
Attend PRC hearing for approval.