SP084 Selection Schedule

July 13, 2021

August 13, 2021

August 16 - August 20, 2021

August 25, 2021

August 30 - September 8, 2021

September 9, 2021

September 13 - September 17, 2021

September 20 October 8, 2021

October 8, 2021

October 11, 2021

October 11, 2021 - May 20, 2022

July 1, 2022

Advertise RFQ for Design Team

Submittals due

Selection committee evaluation, creation of oral interview shortlist

Send notification of results to all firms.  Send oral interview criteria to shortlisted firms.

Oral Interviews – meeting times to be determined

Send notification of results to all firms

Negotiate contract

Draft/complete contract and Board of Trustees Action Item

Board of Trustees approval of contract

Anticipate giving notice to proceed

Complete Study

WWU submission of study to OFM and Department of Commerce

Contact Information

Julian Rodgers, Senior Mechanical Engineer, Project Manager

(360) 650-2230